Package: 37921District: 04 SR/Sec: 0080/311 Type: CE 1b Reevaluation Project: I-80 Eastbound Reconstruction
MPMS: 107495County: Luzerne Status: ApprovedFPN: T043571Z001

Package Document

Related Packages:  25157 (Scoping - Approved 08/12/21)   |  32514 (Eval - Approved 12/12/22)

Funding

 Federal Funding?YesFederal Oversight?Yes Federal Oversight Agreement (June 2015)

Describe Federal Oversight:
PS&E, Award, Const. Inspections, Work Orders, Time Extensions, Claims, and FHWA final acceptance.


Type

 Is this project being documented as an emergency project? Yes    No 

 
Phase:  
Reevaluation

 
Classification:  
Categorical Exclusion (Class II)

 
CE Level:  
1b

CE Action:  
Other         
 04       05       06       07       08       09
 10       11       12       13       14       Other                  

 
Reevaluation Reason:  
 Change in scope, impacts and/or mitigation.
 Three or more years since major authorization or phase change.
 Other:

Summary of Reevaluation Changes by Document

Part A: General Project Identification and Description
Proposed plans for the project were revised, including a reconfiguration of the I-80 interchange with SR 309, along with other changes to the project limits, roadway, and stormwater design. Minor modifications were made to the proposed structure plans. The revised construction and structure plans were attached.

Part A: Engineering Information
Traffic data, construction costs, and the detour duration were updated. It was noted that Luzerne County accepted the detour plan and closures at their 9/23/25 Council Meeting.

Part A: Structure(s)
Minor changes to proposed structure information.

Part B: Section A-1
Wetland and waterway impacts were revised to account for design changes and updated wetland limits. The environmental features plans were updated accordingly. Additionally, mitigation for wetland impacts now includes use of a wetland mitigation bank.

Part B: Section A-2
The revised limits of roadway paving along SR 309 include existing groundwater monitoring wells. No additional hazardous waste studies are required, but the wells are still active and must be maintained.

Part B: Section A-3
Threatened and endangered species coordination was updated. All tree cutting must now be conducted during the bat inactive season (November 15 to March 31) as mitigation for protected bat species.

Part B: Section A-4
The design modifications were reviewed, and the project was determined to still be exempt from further Section 106 review.

Part B: Section A-7
The size and location of right-of-way impacts have been revised due to design changes.

Part B: Section C
A second virtual plans display was held from April 23, 2025 to May 19, 2025.

Confirmation of Reevaluation Classification and Level

 Upon reevaluation, as supported by the attached documentation, this project qualifies as a CE Level 1b.


Projects

 
PDOT Project Manager:  
Summer Koziel
 
Federal Project Number:  
T043571Z001

MPMS Projects
Lead?Status/TitleDistrict/CountySR/SecDescription
  107495Active /
I-80 Eastbound Reconstruction
04 / Luzerne0080 / 311Interstate 80 Eastbound reconstruction and bridge replacement on I 80 EB/WB over SR 309, County Road and Nescopeck Creek, and Linesville Creek, in Butler, Dennison and Foster Townships and White Haven Borough, Luzerne Co.
*The last time MPMS data was added or refreshed was on Tuesday, 03 March 2026 01:01 PM.


Project Funding & Fiscal Constraint
MPMSFD $ROW $UTL $CON $TIPLRTP Date
107495
   113,000,000
118,000,000
FFY 2025 Interstate TIP
FFY 2027 Interstate TIP
 
For federally funded projects where the construction phase (and if needed, ROW and/or utilities phases) is not programmed on the current TIP, remarks provide a detailed reference to the current LRTP identifying full funding for the project.

"LRTP Date" is the date of the last adopted Long Range Transportation Plan.
Refer to May 2017 FHWA "Memorandum Clarifying Fiscal Constraint." See the help files for more detailed information.


Editors

 Names & Groups:Brionna Marks/PennDOT BP-000011
Christina N Stouffer/PennDOT BP-000121
DEB HOOVER/PennDOT BP-000011
Emily Laychock/PennDOT BP-000011
Gregory P Augustine/PennDOT
JOSEPH PASSMORE/PennDOT BP-000011
Kyle N Brubaker/PennDOT BP-000121
Margaret H Schuckman/PennDOT BP-000121
Michael A Cera/PennDOT BP-000010
Nathan G Bevan/PennDOT BP-000010

All District 04 Users


Reviewers

System User NamesNon-System / Other Addresses
 Notify These Additional Emails Upon Approval:Nick Freethy/PennDOT
Ralph D Del Rosso/PennDOT
Steve M Fisher/PennDOT
Summer Koziel/PennDOT



Package was submitted on Wednesday, 18 March 2026 11:18 AM by Nick Freethy/PennDOT


 Email NotifyReviewed ByDate/Time
 
EM:
Kevin J Hendrickson/PennDOT
Kimberly Pabyan/PennDOT
Kimberly Pabyan/PennDOTWed, 03/18/26 11:49 AM
 
ADE:
Susan E Hazelton/PennDOT
Susan E Hazelton/PennDOTWed, 03/18/26 12:18 PM
 
DE:
Jonathan A Eboli/PennDOT
Jonathan A Eboli/PennDOTWed, 03/18/26 12:44 PM




Document Created By:  JOSEPH PASSMORE
10/02/24  02:54 PM

Last Modified By:  Jonathan A Eboli
03/18/26  12:45 PM

 
An ECMS PDC was found for MPMS 107495 -- clearance for package #37921 was successfully added/updated.<br>XML REQUEST for MPMS 107495...
<?xml version="1.0" encoding="utf-8"?>
<soap:Envelope xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema" xmlns:soap="http://schemas.xmlsoap.org/soap/envelope/">
<soap:Body>
<updateCEEChecklistItem xmlns="https://www.ecms.penndot.pa.gov/ECMSWebService/services/WSCEESInterface/updateCEEChecklistItemResponse">
<userId>ceeUser1</userId>
<password>ceeUser1</password>
<ecmsProjectNum>107495</ecmsProjectNum>
<ceeItemNumber>37921</ceeItemNumber>
<clItemNumber>02</clItemNumber>
<actionDate>2026/03/18</actionDate>
<clApprBy>Jonathan A Eboli</clApprBy>
<ceeDocLink><![CDATA[https://dominoappsbp.penndot.pa.gov/ceea/ceeamain04.nsf?Open&UrlPackageId=37921]]></ceeDocLink>
</updateCEEChecklistItem>
</soap:Body>
</soap:Envelope>
-----------------------------------------------------------------------------
XML RESPONSE for MPMS 107495...
<soapenv:Envelope xmlns:soapenv="http://schemas.xmlsoap.org/soap/envelope/" xmlns:soapenc="http://schemas.xmlsoap.org/soap/encoding/" xmlns:xsd="http://www.w3.org/2001/XMLSchema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance"><soapenv:Header/><soapenv:Body><p461:updateCEEChecklistItemResponse xmlns:p461="http://webservices.ecms.dot.state.pa.us"><updateCEEChecklistItemReturn><errorMessage/><ceeItemQueued>0</ceeItemQueued><result>SUCCESS</result></updateCEEChecklistItemReturn></p461:updateCEEChecklistItemResponse></soapenv:Body></soapenv:Envelope>
-----------------------------------------------------------------------------
YesMilestone PE Phase data successfully sent for MPMS 107495<br>XML REQUEST for MPMS 107495...
<?xml version="1.0" encoding="utf-8"?>
<soapenv:Envelope xmlns:soapenv="http://schemas.xmlsoap.org/soap/envelope/" xmlns:web="http://webservice.mpms.dot.state.pa.us">
<soapenv:Header/>
<soapenv:Body>
<web:updateCeMilestone>
<milestoneDT>03/18/2026</milestoneDT>
<milestoneID>00130</milestoneID>
<mpmsNumber>107495</mpmsNumber>
</web:updateCeMilestone>
</soapenv:Body>
</soapenv:Envelope>
-----------------------------------------------------------------------------
XML RESPONSE for MPMS 107495...
<soap:Envelope xmlns:soap="http://schemas.xmlsoap.org/soap/envelope/"><soap:Body><ns2:updateCeMilestoneResponse xmlns:ns2="http://webservice.mpms.dot.state.pa.us"><return>true</return></ns2:updateCeMilestoneResponse></soap:Body></soap:Envelope>
-----------------------------------------------------------------------------
Yes